G702 Line-by-Line Explanation
The G702 is the summary page of the pay application. It shows the contract sum, approved changes, earned to date, retainage, previous payments, and the amount due now.
In plain English: the G703 shows the line-item math, and the G702 summarizes it. If the summary does not tie to the continuation sheet, reviewers usually stop the approval.
The G702 is the summary cover sheet that rolls up totals from your continuation detail (your G703/SOV). Reviewers don’t want “close enough.” They want totals that tie out cleanly, every month.
Why the G702 gets so much scrutiny
The G702 looks simple compared to the continuation sheet, but this is usually the page a reviewer looks at first. It is the summary page that answers the big questions:
- What is the contract sum right now?
- How much has been earned to date?
- How much retainage is being held?
- How much was previously paid?
- What is due now?
If the G702 looks wrong, reviewers often assume the package behind it is wrong too. That is why this page works best when used alongside your full preparation workflow: How to Fill Out G702/G703, the broader Construction Payment Application Guide, and the rejection checklist.
What the G702 Actually Does
Think of the G702 as the “owner-friendly” summary of your pay application. It answers:
- What’s the contract value right now, including approved change orders?
- How much work has been completed and stored to date?
- How much retainage is being withheld?
- How much has been paid previously?
- What’s due on this application?
The Tie-Out Checks Reviewers Use
Before we go line-by-line, here are the checks that catch most problems:
- G702 totals match G703 totals (completed & stored to date, retainage, amount due).
- SOV total equals current contract sum (original contract + approved change orders).
- Previous totals do not change month-to-month (this month’s “previous” equals last month’s “to date”).
- No line item has to-date > scheduled value unless the scheduled value was updated via approved CO.
- Stored materials are backed up and don’t magically stay “stored” forever.
G702 Line-by-Line (Plain English)
Note: Exact labeling can vary by project templates. The logic is the same: contract value → earned → retainage → prior payments → amount due.
Lines 1–3: Contract Value
- Line 1 – Original Contract Sum: the starting dollar amount in the executed contract or subcontract.
- Line 2 – Net Change by Change Orders: the total of approved change orders, including adds and deductions.
- Line 3 – Contract Sum to Date: line 1 + line 2. This must match the total scheduled value of your SOV.
Lines 4–5: Work Completed & Stored
- Line 4 – Total Completed & Stored to Date: cumulative installed work + materials stored, if the contract allows them. This should tie to the G703 totals.
- Line 5 – % of Completion: line 4 ÷ line 3. It’s a sanity check, not a substitute for line-item support.
Line 6: Retainage
Retainage is the amount withheld per contract terms. Where people get into trouble is applying it inconsistently: by line item one month, then summary-only the next, or applying it differently to stored materials.
- Line 6 – Retainage: the withheld amount based on contract rules, percentages, exclusions, and releases.
Line 7: Earned Less Retainage
- Line 7 – Total Earned Less Retainage: line 4 minus line 6. This is the earned value after withholding.
Line 8: Previous Payments
- Line 8 – Less Previous Certificates for Payment: total of prior approved payments or certificates.
Line 9: Payment Due This Application
- Line 9 – Payment Due: line 7 minus line 8. This is the amount you’re requesting now.
Line 10: Balance to Finish
- Line 10 – Balance to Finish: line 3 minus line 4. It’s a contract-level “what’s left” number.
Common G702 Mistakes That Trigger Rejections
- Contract sum mismatch: change orders approved but not reflected in line 2/3 and the SOV.
- G702/G703 mismatch: summary totals don’t match the continuation sheet totals.
- Previous totals changed: someone edited a prior month number.
- Retainage inconsistency: retainage applied differently month-to-month.
- Stored materials confusion: billed without backup or never reduced when installed.
How PayAppPro Helps (Without Spreadsheet Drama)
- Keeps your SOV, previous totals, and current period entries tied together
- Rolls G703 line totals into a clean G702-style summary automatically
- Helps prevent over-billing beyond scheduled values
- Reduces “revise and resubmit” errors caused by broken formulas
- Tracks stored materials and supporting history more cleanly across billing periods
AIA-style outputs. Built-in checks. Fewer kickbacks.