Example Completed G702 & G703 Pay Application (AIA-Style)

This page shows a read-only example of how a completed G702 summary and G703 continuation sheet typically look when filled out correctly.

Use this as a visual reference only. Numbers are illustrative. PayAppPro outputs are AIA-style and are not official AIA® Contract Documents.

Designed for subcontractors, project accountants, and small GCs who bill monthly using G702/G703.

G702 — Application and Certificate for Payment (Example)

The G702 summarizes the overall contract status and calculates the Current Payment Due based on values rolled up from the G703.

Original Contract Sum $250,000.00
Net Change by Change Orders $15,000.00
Contract Sum to Date $265,000.00
Total Completed & Stored to Date $132,500.00
Retainage (10%) ($13,250.00)
Current Payment Due $119,250.00
Balance to Finish $132,500.00
In PayAppPro, these values are calculated automatically from the continuation sheet below.

G703 — Continuation Sheet (Example)

The G703 breaks the contract into Schedule of Values (SOV) line items and tracks progress month over month.

# Description of Work Scheduled Value Prev Completed This Period Total Completed % Complete Balance
1 Mobilization $25,000 $25,000 $0 $25,000 100% $0
2 Rough Carpentry $95,000 $40,000 $22,500 $62,500 66% $32,500
3 Finish Carpentry $145,000 $0 $45,000 $45,000 31% $100,000
In PayAppPro, percentages, totals, retainage, and rollups are calculated automatically.

What This Example Demonstrates

  • How G703 line items roll up into the G702 summary
  • Consistent math across periods
  • Clear retainage handling
  • Reviewer-friendly structure

This same structure is used when exporting PDFs from PayAppPro.