AIA G702/G703 Rejection Checklist
Before you submit, make sure your G702 totals tie to the G703/SOV, prior-period values roll forward cleanly, retainage is consistent, and required backup is attached.
This page is the final check page. It is meant to catch issues before the reviewer does.
Run through this checklist before submitting your AIA-style G702/G703 pay application package. It’s designed to catch the same issues reviewers kick back every month: tie-outs, retainage drift, SOV mismatches, stored materials problems, and missing documents.
How reviewers are looking at your package
Most reviewers are not trying to “grade” your project team. They are trying to answer a short list of questions as fast as possible:
- Do the G702 totals tie to the G703 / SOV detail?
- Does this month’s package roll forward cleanly from the last approved application?
- Are retainage, change orders, and stored materials handled the same way they were supposed to be handled last month?
- Are the attachments complete enough to approve without follow-up?
That is why this checklist works best when used alongside your actual preparation workflow. If you need the broader “what belongs in the package” view, start with Construction Payment Application Guide. If you need the actual prep walkthrough, see How to Fill Out AIA-Style G702/G703.
Need the “generate it” workflow (not just the checklist)?
Use the hub pages for practical steps, examples, and how PayAppPro keeps your G702 totals tied to your G703/SOV automatically.
- G702 totals don’t tie to the bottom totals on G703/SOV.
- Prior period values changed without explanation/approval.
- Retainage applied differently this month than last month.
- Change orders not reflected in contract sum / SOV scheduled values.
- Stored materials billed without backup—or never “move” into work-in-place.
- Overbilling (line total exceeds scheduled value).
- Missing attachments (lien waivers, invoices, conditional releases, etc.).
Before You Submit, Confirm:
1) Math tie-outs (G702 ↔ G703 ↔ SOV)
- ☑ G702 totals match G703 totals exactly (completed + stored to date, retainage, earned, prior payments, amount due).
- ☑ G703 bottom totals match the sum of line items (no missing lines, no “mystery” rounding).
- ☑ No line item is overbilled (total completed + stored to date does not exceed scheduled value).
- ☑ Percent complete and “balance to finish” are reasonable relative to the scheduled value.
2) Rollforward integrity (prior-to-date stability)
- ☑ Previous billing amounts are unchanged (unless you’re issuing an approved correction).
- ☑ This period values are added cleanly (no “moving” prior work between buckets).
- ☑ Prior payments/certificates match your project’s approved history.
3) Retainage consistency
- ☑ Retainage percentage matches the contract (and any retainage release rules).
- ☑ Retainage is applied consistently month-to-month (same buckets, same logic).
- ☑ If retainage is partially released, the release is documented and totals still reconcile.
4) SOV + change order alignment
- ☑ Your Schedule of Values matches the approved version (scope and values).
- ☑ Approved change orders are reflected in the contract sum and/or scheduled values (depending on how your project handles it).
- ☑ Pending/unapproved changes are not quietly baked into scheduled values.
5) Stored materials sanity checks
- ☑ Stored materials are supported (invoices/receipts + photos/location, if your reviewer requires it).
- ☑ Stored values don’t get “double counted” when materials are installed (stored should decrease as work-in-place increases).
- ☑ Retainage on stored materials follows the project rule.
6) Attachments & required documents
- ☑ Required lien waivers are attached (conditional vs unconditional, progress vs final, correct tier).
- ☑ Any required subcontractor/vendor backup is included (if your GC/owner requires it).
- ☑ The pay app period end date and backup documents reference the same period.
Download: Want a printable version? Grab the PDF checklist.
7) Packaging & reviewer friendliness
- ☑ Application number + period dates are clearly shown and consistent across pages.
- ☑ PDF is clean (no cut-off tables, no unreadable tiny fonts, no sideways pages).
- ☑ If you include backup, keep it organized (one combined PDF, or labeled files that match the checklist).
Built-in checks help catch issues before submission.