Reviewer Perspective

How General Contractors Review Pay Applications

Submitting a pay application is only half the process. Understanding how a general contractor reviews it is what determines whether you get paid on time — or receive a rejection notice that delays your cash flow another 30 days.

Most general contractors follow a structured internal review process before approving a pay application. Whether the billing format is AIA-style G702/G703 or a custom progress billing template, the review priorities are remarkably consistent.

New to the structure of progress billing? Start with How to Fill Out AIA-Style G702 & G703.

Step 1: Math & Reconciliation Review

The first filter is always numerical accuracy. If the numbers don’t tie out, the review often stops immediately.

  • Do summary totals match continuation sheet totals?
  • Do prior-to-date amounts roll forward correctly?
  • Does retainage calculate consistently with prior months?
  • Does the contract sum reflect approved change orders?

Even small discrepancies raise red flags because GCs often have to submit consolidated billing to owners or lenders. One incorrect subcontractor pay app can delay the entire project billing cycle.

Helpful: Rejection Checklist

Step 2: Schedule of Values Integrity

The Schedule of Values (SOV) acts as the backbone of progress billing. GCs verify that:

  • No new line items were introduced without approval
  • Values weren’t shifted between scopes
  • No line exceeds its scheduled value
  • Percent complete appears reasonable for the stage of work

If the SOV drifts from the approved version, it creates reconciliation issues upstream.

Learn more: What Is a Schedule of Values?

Step 3: Change Order Verification

Change orders are one of the most common rejection triggers. GCs confirm:

  • Only approved COs are included
  • Contract sums reflect signed documentation
  • CO values match executed agreements exactly

Guide: How to Bill Change Orders Properly

Step 4: Stored Materials & Documentation

Stored materials are carefully scrutinized. GCs verify:

  • Invoices or supplier documentation are attached
  • Materials meet contract requirements for billing
  • Stored materials don’t remain stagnant month after month

Read: How to Bill Stored Materials

Step 5: Compliance & Risk Review

Before approval, GCs verify compliance documentation:

  • Correct lien waivers attached
  • Proper billing period dates
  • Insurance or certified payroll if required

Background: Lien Waivers in Construction

What Happens Inside the GC Office

In many firms, the review process includes multiple checkpoints:

  1. Project Manager reviews progress and field alignment
  2. Accounting verifies math and compliance
  3. Executive or owner-level review for large projects
  4. Submission to architect, owner, or lender

If an issue is identified at any stage, the billing cycle may pause until corrections are made.

Real-World Scenario

A subcontractor submits an $85,000 pay application. During review, the GC notices retainage was calculated at 5% instead of the contractually required 10%. Because prior months used 10%, the historical totals no longer reconcile.

The pay application is returned for correction. The owner billing deadline passes. Payment is delayed 30 days.

Small discrepancies can create large cash flow consequences.

Common Red Flags That Trigger Rejection

  • Prior billing numbers changed without explanation
  • Overbilling beyond scheduled value
  • Retainage drift
  • Unapproved change orders included
  • Missing backup documentation

Frequently Asked Questions

How long does it take a GC to review a pay application?

Typically 2–7 business days internally, depending on project size and documentation completeness.

Can a GC partially approve a pay application?

Yes. GCs may adjust or reduce line items if they disagree with percent complete or documentation.

What happens after approval?

The pay application is typically rolled into the owner’s billing package or lender draw request.

Submit Cleaner Pay Applications

When your billing ties out every month, GC reviews move faster.

Build an AIA-Style Pay Application

Related guides: Construction Progress Billing | Rejection Checklist